Steps to New Construction

  1. Call 903-763-2203 to order a new connection.
  2. Site visit by WCEC field service representative.
  3. WCEC representative relays options and associated fees.
  4. Member selects option, pays fees and completes easements. (All required before next step).
  5. WCEC secures permits.
  6. Dig Tess line locates are completed.
  7. Job is released for construction and goes in queue.
  8. From this point, the wait averages 2-4 weeks for overhead line and 4-5 weeks for underground.