Rates & Fees

The base rates listed below are adjusted upward or downward depending on the cost of wholesale power. This adjustment is known as the Power Cost Recovery Factor (PCRF). The PCRF is applied to each kWh billed.

Schedule A

(Single phase service less than 50 kW)

DescriptionCharge
Monthly Base Charge$17
Minimum Bill Charge$17
Energy Charge per kWh$0.06667

Schedule GS

(3 phase up to max 50 kW demand)

DescriptionCharge
Monthly Base Charge $35
Energy Charge per kWh, first 1500 $0.0671
Energy Charge per kWh, over 1500 $0.0592
Demand Charge per kW, first 10 $0
Demand Charge per kW, over 10 $5.50

Schedule LP

(Single or 3 phase service consistently over 50 kW Demand)

DescriptionCharge
Monthly Base Charge $140
Energy Charge per kWh $0.03858
Demand Charge, per Billing kW $7
Minimum Monthly Charge
(The greater of the following)
1. $1.15 per KVA of installed transformer capacity.
2. The Base Charge plus the Billing Demand Charge

Schedule OL
DescriptionCharge
New Installation $37

Unmetered

DescriptionCharge
Standard LED arm lamp $8 per month
Power Flood LED lamp $13.30 per month
Large LED arm lamp $13.30 per month

Metered

DescriptionCharge
175 Watt MV lamp$3 per month
100 Watt HPS lamp$3 per month
Standard LED lamp $6.80 per month
400 Watt MV lamp $7.54 per month
250 Watt HPS lamp $7.54 per month
Power Flood LED lamp $10 per month
Large LED arm lamp $10 per month
Non refundable pole installation $150 per pole
Pole Rental, 2 poles max per light$0.75 per pole per month
Transformer charge $8 per month

All mercury vapor options are closed to new customers and are applicable to those being served as of October 1, 2007.

Line Extension Charges & Allowances

New Construction Credits

DescriptionCredit
Maximum Primary Overhead $450
Maximum Secondary Overhead $0
Maximum Primary Underground $500
Maximum Secondary Underground $500

Line Extension Charges

Description Charge
Overhead Single-Phase Primary and/or Service $6/ft
Overhead Multi-Phase Primary and/or Service $8/ft
Underground Single-Phase Primary $9/ft
Underground Multi-Phase $12/ft
Single Phase Bore (Typical) $8/ft
Single Phase Bore (Under Highway) $24/ft
Multi-Phase Bore (Typical) $10/ft
Multi-Phase Bore (Under Highway) $36/ft
Condemnation Escrow Requirement $10,000
Condemnation Escrow Balance Requirement $500
Switchover Fee$315

Line Extension Examples

Cost Considerations for Converting Existing Service

  • For any conversion of existing service (overhead to underground or vice versa), the above charges will apply, plus the depreciated original cost of any existing line and facilities, less the estimated value of salvage, plus the estimated cost of removing them.

Download the full Member Policies & Schedules (PDF).